News

Community Update Meeting 3/19/19

The next community update meeting is being held tomorrow, Wednesday 3/20, at 6:30pm at the Skyland Workforce Center.

March 19th, 2019|

Construction Update 3/8/19

Please find the below the construction updates for Skyland Town Center: Saturday, March 9 – No OFF SITE work There will be ON SITE work Week of March 11 – OFF SITE work will continue at the intersection of Good [...]

March 8th, 2019|

Construction Update 3/1/19

Please find below construction updates for Skyland Town Center: Saturday, March 2 – No OFF SITE nor ON SITE work Week of March 4th – Continued OFF SITE Work at Naylor and Good Hope Road intersection Typical ON SITE work

March 1st, 2019|

Construction Update 2/22/19

Please find below construction updates for Skyland Town Center: Saturday, February 23 – No OFF SITE work Typical ON SITE work, weather pending Week of February 25 – Continued OFF SITE Work at Naylor and Good Hope Road intersection Typical [...]

February 22nd, 2019|

Construction Update 2/8/19

Please find listed below construction updates for Skyland Town Center: Saturday, February 9, 2019 – No OFF SITE work We anticipate construction activities for ON SITE work, pending weather conditions Week of 2/11 – OFF SITE work continues to be [...]

February 8th, 2019|

Construction Update 2/1/19

Please find listed below construction updates for Skyland Town Center: Saturday, February 2, 2019 – There will be no OFF-SITE work There will be ON-SITE work Week of February 4, 2019 – Continued OFF-SITE work will be focused at the [...]

February 1st, 2019|

Construction Update 1/18/19

Please find listed below construction updates for Skyland Town Center: There will be no OFF-SITE work on Saturday and Monday There will be limited ON-SITE work on Saturday There will also be limited ON-SITE work on Monday as required testing [...]

January 18th, 2019|

Construction Update 1/11/19

Please find listed below the construction updates for Skyland Town Center: Saturday, January 12 – on-site construction activities only Week of January 14 – Comcast will be relocating lines along Naylor and Good Hope Road Typical on-site construction activities

January 11th, 2019|

Construction Update 1/4/19

Please find listed below construction activity updates for Skyland Town Center: Saturday, 1/5 – on-site construction activities only Week of 1/7 – Continued on-site construction Off-site work at various intersections that will not affect traffic

January 4th, 2019|

Construction Update 12/28/2018

Please find below the construction updates for Skyland Town Center: Saturday, December 29 – full construction day for ON-SITE work Monday, December 31 – full construction day for both ON-SITE and OFF-SITE work Tuesday, January 1 – no work

December 28th, 2018|