Site Work Update 2/2/18

As construction progresses on Skyland Town Center, we would like to inform you that there will be no onsite or offsite work this weekend 2/3-2/4. Normal construction operations will resume Monday 2/5.

Community Meeting and Construction Update 1/19/18

- Onsite work is planned for Saturday 1/20/18 beginning at 7am; there will be no onsite or offsite work Sunday 1/21/18. - Onsite and offsite work will re-commence on Monday 1/22/18 and continue through the week. There is a possibility [...]

Construction Update 1/5/18

In an effort to keep you informed of the progress at Skyland Town Center, please note the following construction updates: - On Saturday 1/6, construction equipment will be delivered to the site. It will take a week to set this [...]

Site Work Update 12/19/17

In an effort to keep you informed of the progress at Skyland Town Center, please note the following construction updates.  Minor construction activity in the public space surrounding the project will recommence Wednesday 12/27. We anticipate these activities lasting approximately two [...]

Community Meeting 12/7/17

Please join us for a construction update meeting on Thursday, December 7th at 6:30pm at the Skyland Workforce Center (2509 Good Hope Rd SE, Washington, DC 20020). This conversation will focus primarily on a schedule update for the building construction.

Site Work Update 11/17/17

Please note that there will no onsite or offsite work in observance of the Thanksgiving holiday beginning at noon on Wednesday November 22nd and extending through the weekend.  Construction activities will resume on Monday November 27th.

11/2/17 Community Meeting Cancellation

Please note that our meeting on Thursday, November 2nd at 6:30pm for a Skyland Town Center construction updated is CANCELLED.  There is no on-site or off-site work currently. The anticipated recommencement of work will be towards the end of November.

Construction Update 10/20/17

The next community meeting to discuss construction updates and development of the Skyland Town Center project will be Thursday, November 2nd at 6:30pm.  This meeting will be held at the Skyland Workforce Center, 2509 Good Hope Rd SE.

Construction Update 8/28/17

Please note the following construction updates: • Work on the new bus stop location on Naylor Road has begun; we anticipate this work being completed at the end of September. • Due to the phased construction of the bus stop, [...]

Ward 7 & 8 Development Boom

Skyland Town Center's new retail options and modern apartments are named by the Washington Business Journal as major contributors to the transformation of Wards 7 & 8.  Read the full story here.