Construction Updates

Construction Update 7/20/17

Please note the following update for construction at Skyland Town Center: - We anticipate the start of offsite improvements for Phase II to begin in August. - Onsite work continues in preparation for excavation activities of Block 2; excavation is [...]

July 20th, 2017|

Construction Updates Week of 12/22/16

Please note that the Skyland Town Center site will be closed for work over the holiday from Friday 12/23 through Monday 12/26.

December 22nd, 2016|

Construction Updates: Week of 4/18/2016

Site Activity: Utility Work, Landscape & Retaining Wall Progress In our continued effort to keep you informed about the progress at Skyland Town Center, please note the following construction update. As you have noticed, utility work in the public [...]

April 18th, 2016|

Construction Updates: Week of 3/22/2016

Site Activity: Utility Improvements, Retaining Wall Progress & Parking Notification In an effort to keep you updated about the progress at Skyland Town Center, please note the following construction update details. Utility improvement work in the public space continues and [...]

March 22nd, 2016|

Construction Updates: Week of 12/11/2015

Site Activity: Deep Dynamic Compaction & Vibration Monitoring Please be advised that work will be occurring onsite at Skyland Town Center this Saturday, December 12th from approximately 7am to 4pm. The required permits have been obtained. Additionally, please be advised [...]

December 11th, 2015|

Construction Updates: Week of 11/11/2015

Site Activity  Utility Construction & Sanitary Work Please be advised that the utility construction work on Alabama Avenue is on track, with 140 feet of new water line installed. We intend to begin sanitary work by November 13th per the [...]

November 11th, 2015|

Construction Update: Week of 10/22/15

Site Activity  Utility Construction Utility construction work will start October 26, 2015 and continue for approximately six (6) months. This work includes installation of a new water line, sanitary laterals, and storm lines. Work will start at the eastern [...]

October 22nd, 2015|

Construction Updates: Week of 10/22/15

Site Activity  Utility Construction Utility construction work will start October 26, 2015 and continue for approximately six (6) months. This work includes installation of a new water line, sanitary laterals, and storm lines. Work will start at the eastern [...]

October 22nd, 2015|

Construction Update: Week of 9/21/15

Site Activity  Deep Dynamic Compaction and Installation of Water and Sanitary Lines This is an update on construction work at Skyland Town Center. Site work is underway to prepare the site for the future construction of buildings. We are [...]

September 21st, 2015|

CONTACT US

TO LEARN MORE ABOUT SKYLAND

REACH OUT