Construction Updates: Week of 10/22/15

Site Activity  Utility Construction Utility construction work will start October 26, 2015 and continue for approximately six (6) months. This work includes installation of a new water line, sanitary laterals, and storm lines. Work will start at the eastern [...]

October 22nd, 2015|

Construction Update: Week of 9/21/15

Site Activity  Deep Dynamic Compaction and Installation of Water and Sanitary Lines This is an update on construction work at Skyland Town Center. Site work is underway to prepare the site for the future construction of buildings. We are [...]

September 21st, 2015|